DETAILS OF WORK COMPLETED
Name : PVIP - Rectification works to preventing leakage from Ch 1.100 Km to 1.200 Km of Manjappetty sub branch canal including reconstruction of chamber near pipe syphon.
(Brief Description) Lining work and reconstruction of chamber
Name of Division PVIP Division No:2
Type of Contract open tender
AS No. Date and Amount PVIPDII/2020/717/P2 Dated: 05-11-2020
TS No. Date and Amount PVIPDII/2020-2021/2020/717/P2 Dated:06-11-202
Agreement No. and Date 17/AEE4/PVIP/2020-21 28-12-2020
Accepted PAC Rs.3,36,965/-
Name and Adress of Contractor M.M.Shanavas, Mezhukattil house, Edathala.p.o
Date of Commencement of Work 44195
Period of Completion 6 Months
Date of completion originally fixed 44377
Extended Date of Completion nil
Actual Date of Completion 44278
Physical Progress up to date 100%
Latitude and Longitude Lat 10.099554
  Long 76.441856