| DETAILS OF WORK COMPLETED | |
| Name : | PVIP-Natural Calamity Re-construction of washed out culvert and side protection wall of the inspection road at Ch: 22/500 km of HLC |
| Brief Description | Re-Construction of washed out Culvert at HLC inspection road during Flood 2018 |
| Name of Division | PVIP DIVISION NO II, ALUVA |
| Type of Contract | TENDER |
| AS No. Date and Amount | 180/2018-2019 |
| TS No Date and Amount | 405/2018-2019 |
| Agreement No. and Date | 01/EE-2/PVIP/2019-20 Dated 04/06/2019 |
| Accepted PAC | Rs 3199777.67 |
| Name and Adress of Contractor | Shri Dony Paul, Meprathmalil House, Vengola PO, Perumbavoor |
| Date of Commencement of Work | 43630 |
| Period of Completion | 1 Year |
| Date of completion Originally fixed | 44177 |
| Extended Date of Completion | 44255 |
| Actual Date of Completion | 44254 |
| Physical progress up to date | Work Completed |
| Latitude and Longitude | 10.012789, 76.474561 |