| DETAILS OF WORK COMPLETED | ||
| Name : PVIP-Rectification works to bed and sides of Paipra M.D. at Ch:3/100 km | ||
| Construction of side wall and wearing coat to bed with C.C. 1:3:6 to prevent leakage | ||
| Name of Division | PVIP Division No 1 Perumbavoor. | |
| Type of contract | Item Rate | |
| A.S No. Date and Amount | PVIPDI/2021/610/P2 Dated: 19-05-2021 Rs.660000/- | |
| T.S No. Date and Amount | PVIPDI/2021-2022/2021/610/P2 Dated:31-05-2021 Rs.660000/- | |
| Agreement No and Date | 1/AEE1/PVIP/2021-22 dtd 24/06/21 | |
| Accepted PAC | Rs. 441,613.37 | |
| Name and Address of cntractor. | A.R. Cheriyan, Ambalakkattu, Thrikariyoor |
|
| Date of commencement of work | 44375 | |
| Period of completion | 6 months | |
| Date of completion originally fixed. | 44553 | |
| Extended Date of completion | Nil | |
| Actual Date of completion | 44435 | |
| Physical progresss upto date | 100% | |
| Latitude and Longitude | 10.052291 76.566678 |
|