DETAILS OF WORK COMPLETED | |
MVIP-Kurumulloor major distributory from ch.8700m to 10748m.- Improvements to thodu from ch.9430m to 10363m for forming the tail end of LBMC, including CD works | |
Construction of Kurumalloor distributory tail end(MVIP tail end) including open canal and flume works | |
Name of Division | Division no IV Piravom |
Type of Contract | Contract |
AS No. Date and Amount | G.O.(Rt)No.1000/2016/WRD Dtd 21/12/2006 |
TS No Date and Amount | 189/2016-17 dtd 10/02/2017 |
Agreement No. and Date | 01/SEPCM/2017-18 dtd 02/05/2017 |
Accepted PAC | 291.41 lakhs |
Name and Adress of Contractor | Mathew Korah, Govt contractor |
Date of Commencement of Work | 42864 |
Period of Completion | 12 months |
Date of completion Originally fixed | 43228 |
Extended Date of Completion | 43585 |
Actual Date of Completion | 43580 |
Physical progress up to date | completed |
Latitude and Longitude | 9.672006, 76.529264 |