| DETAILS OF WORK COMPLETED | |
| MVIP-Kurumulloor major distributory from ch.8700m to 10748m.- Improvements to thodu from ch.9430m to 10363m for forming the tail end of LBMC, including CD works | |
| Construction of Kurumalloor distributory tail end(MVIP tail end) including open canal and flume works | |
| Name of Division | Division no IV Piravom |
| Type of Contract | Contract |
| AS No. Date and Amount | G.O.(Rt)No.1000/2016/WRD Dtd 21/12/2006 |
| TS No Date and Amount | 189/2016-17 dtd 10/02/2017 |
| Agreement No. and Date | 01/SEPCM/2017-18 dtd 02/05/2017 |
| Accepted PAC | 291.41 lakhs |
| Name and Adress of Contractor | Mathew Korah, Govt contractor |
| Date of Commencement of Work | 42864 |
| Period of Completion | 12 months |
| Date of completion Originally fixed | 43228 |
| Extended Date of Completion | 43585 |
| Actual Date of Completion | 43580 |
| Physical progress up to date | completed |
| Latitude and Longitude | 9.672006, 76.529264 |