Thottappally Spillway Desilting
Sand deposited downstream of Thottappally spillway was removed to attain a width of 360m at pozhy mouth.
Initial Estimated Quantity to be removed
|
2,20,031.25 cum |
Initial Proposed Date of completion | 31/07/2020 |
Additional Estimated Quantity removed to attain a width of 360m at pozhy mouth | 22,800 cum |
Proposed date of Achieving 300m at Pozhy Mouth
|
22/07/2020 |
Total Qty to be removed to attain a width of 360m at pozhy mouth
|
2,42,831.25 cum |
Proposed Date for achieving targeted width of 360m | 28/07/2020 |
Actual completion of work | 23/07/2020 |
Desilting was completed on 23.07.2020 and the Pozhy was Opened on 30.07.2020